Policy analysis of the second CRMA selection: notes that the 24-month permitting commitment is a legal obligation on member states but lacks enforcement mechanism if individual national permitting authorities delay; documents that the first-list projects (47 projects selected July 2024) have seen 12 of 47 receive initial permits within the statutory window, with 35 still pending; questions whether the second list will improve the implementation rate.

“The EU's second CRMA strategic project list adds 47 projects but faces questions over whether the 24-month permitting commitment will be enforced.”