Stargate's Abilene flagship goes live as Crusoe stacks $15bn to finish it

The 1.2GW Texas campus runs on Oracle Cloud with first GB200 racks delivered; Crusoe's $1.38bn Series E funds the expansion as SoftBank completes its $41bn into OpenAI

AI·Infrastructure· active Whose Money·The Long Game ·9 takes · ·rbtfl upd Jun 25, 2026
post

The split

The same story, as told by newsrooms in different countries. Their words, attributed and linked.

United States

CNBC

“OpenAI's first data center in the $500 billion Stargate project is open in Texas.”

US businessread the original ↗

United States

IntuitionLabs

“Oracle and OpenAI's ~$300B deal: an AI-infrastructure commitment that loads Oracle's balance sheet.”

infrastructure analysisread the original ↗

post

Summary

Stargate's flagship in Abilene, Texas is operational: a ~1.2GW campus of 4m sq ft running on Oracle Cloud Infrastructure, with Oracle delivering the first Nvidia GB200 racks and early training/inference workloads under way; full completion is expected mid-2026. Developer Crusoe raised a $1.38bn Series E ($10bn valuation) to fund the expansion, bringing ~$15bn total to the Texas project. Oracle and Openai have agreed to up to 4.5GW of additional Stargate capacity (>$300bn over five years), and SoftBank has completed its $41bn investment into Openai. The financing is also the fault line: Oracle's leverage and OpenAI's losses anchor the circular-financing debate.

By the numbers

  • ~1.2GW / ~4m sq ft, Abilene campus capacity and footprint.
  • $1.38bn, Crusoe Series E (~$10bn valuation); ~$15bn total to the Texas project.
  • 4.5GW / >$300bn, additional Oracle–OpenAI Stargate capacity / five-year value.
  • $41bn, SoftBank investment completed into OpenAI.

Why it matters

Abilene is the proof-of-concept that the $500bn Stargate vision can pour concrete and run GPUs. The same deals that finance it, Oracle's debt-funded cloud build against OpenAI's loss-making commitments, are exactly what credit markets watch for the first crack.

What to watch

  • Mid-2026 full-campus completion and GB200 ramp at Abilene.
  • Oracle credit metrics (debt-to-equity, CDS spreads) as commitments grow.
  • Whether the 4.5GW additional capacity gets sited and powered.